his article describes an approach for hardening high-voltage power substation control electronics from high-altitude electromagnetic pulse (HEMP) that would occur if a nuclear weapon were detonated in space. While we hope that this type of electromagnetic event never occurs, it is a possibility, and the impact on unprotected electronics and the power grids that they control could be severe. In the case of HEMP, a single high-altitude nuclear burst could expose thousands of power substations to high-frequency transients within one power cycle, creating essentially a simultaneous distributed event for which the power grid was not designed.
While the emphasis for this article will be on the protection from early-time (E1) HEMP, it will also discuss the additional efforts that can be made to protect the electronics from intentional electromagnetic interference (IEMI) produced by electromagnetic weapons. By considering both the E1 HEMP and IEMI together, we cover the main high frequency transient high-power EM (HPEM) threats that have become important in recent years.
As described in the work in IEC SC 77C, while high power electromagnetic (HPEM) disturbances are low probability events, they can be protected against with existing protection technology and often at low cost. The field of electromagnetic compatibility (EMC) is well established, and methods for shielding against electromagnetic fields and attenuating conducted transients are widely known. The main issue is to determine the requirements for these protective elements as they relate to E1 HEMP and IEMI.
This article focuses on the fact that the electronics found in the control houses of electric power substations are already exposed to high levels of natural power system EM transients and are therefore required to have immunity against high levels of radiated and conducted transients. The major generic EMC standards for establishing immunity tests and test levels for electronics placed in control houses are set forth in IEC 61000-6-5 [1]. By considering the basic immunity of the electronics in the control houses for EMC and the external HEMP and IEMI radiated field waveforms and their coupling to external cables outside of the control house and internal cables (thereby creating conducted transient disturbances), protection methods can be established. The recently developed IEC 61000-5-10 [2] provides different strategies for protection for both new and retrofit applications, relying on several other published IEC SC 77C standards.
In this article, we’ll first review the basic HEMP and IEMI electromagnetic waveforms as discussed in our previously published article in In Compliance Magazine [3]. Next, we’ll describe the basic layout of high voltage substations and the electronics found in a substation control house. Then, we’ll discuss the EMC immunity requirements for the control electronics and how these can be leveraged to determine the specialized HEMP/IEMI protection methods. Following this discussion, we’ll share and describe the techniques for rapidly assessing the existing shielding and penetration protection of an existing control house. Finally, we’ll discuss some of the protection options available.
Figure 2 describes in the frequency domain the relationship between early-time (E1) HEMP and IEMI environments that can be produced from electromagnetic weapons. It also indicates at lower frequencies the typical levels of lightning electromagnetic fields from very near cloud-to-ground strikes. It is important to understand that, while lightning currents and fields are very energetic, they do not extend significantly above 1 MHz in frequency content, as do both the E1 HEMP and IEMI. This means that most grounding and bonding methods used for lightning are not sufficient for the higher frequency content E1 HEMP and IEMI. This will be discussed later in this article.
There are also distribution substations found within towns and cities, but the focus of this article is on the transmission substations due to the much higher amount of power passing through the substation. The loss of power flowing through a few transmission substations in a region can create a severe power supply/load imbalance that can result in a power blackout.
As a simple example, if the voltage on a line decreases rapidly and the current increases sharply, this could be an indication of a line being grounded to a tree, and the relay receiving this information will send a signal to a circuit breaker (along another cable) to disconnect the power line from the step-down transformer to avoid damage. These relays are programmed ahead of time to determine what levels will trigger such a response, and actions are taken automatically without human intervention. These protection relays are therefore critical to the operation of a power substation and the overall power grid.
It is important to understand that for both E1 HEMP and IEMI the electromagnetic transients are created external to the building. There, they couple to external cables, external antennas, and interact with the walls of the control house to penetrate to the inside through apertures (for air flow and doors, for example) and through nonmetallic walls such as concrete. Figure 5 illustrates the types of aspects that should be considered for the penetration of external fields and voltages into a control house.
While it is important to reduce the external radiated and conducted environments associated with E1 HEMP and IEMI, we wish to make the important point that, due to the severe EMC tests required for the individual electronic “boxes,” the reductions required for the radiated and conducted transients from E1 HEMP and IEMI are not as large as would be required for commercial or industrial electronics.
Figure 6 presents the steps required to perform a complete assessment for a control house for both E1 HEMP and IEMI. The first step is to evaluate the shielding effectiveness of the control house from 1 to ~100 MHz for E1 HEMP and from ~100 MHz to ~5 GHz for IEMI. There is a relatively new method available [10] to assess the shielding effectiveness of operating facilities with shielding levels below 50 dB, known as the commercial radio signal assessment method. This method uses measurements of local AM, FM, digital TV, and cellular signals both inside and outside of the building to estimate the amount of attenuation present (see Figure 7 as an example of external signals which are well above the noise).
Through frequency domain to time domain translations, this process can convert any external time domain transient to an internal room time domain transient, as long as the frequency range information acquired is appropriate. This also does not require Federal Communications Commission (FCC) approval of special transmitters and allows a proper plane wave “simulation” of E1 HEMP conditions, as even at 1 MHz, the wavelength is 300 meters, which would require a transmitter standoff of much greater than this distance. Evaluations of this technique have been performed with good results and have been applied to over 100 control houses in the past ten years.
Once the shielding effectiveness has been evaluated over the frequency range of interest, one must then define the E1 HEMP and IEMI waveforms to be applied. IEC 61000-2-9 [5] provides a good example for E1 HEMP, and IEC 61000-2-13 provides several examples for IEMI threats [11]. In addition, since the IEMI EM weapon threat is a local threat, the closest approach to the control building needs to be evaluated. Satellite mapping tools can be used for this purpose.
Once the external EM threats are defined, the internal time field waveforms can be developed using the measured EM attenuation information. The next step is to evaluate the currents and voltages coupled to the internal wiring using coupling evaluations based on random orientations and polarizations performed for different cable lengths. Then, a probabilistic method can be used to select worst-case or average levels of coupling.
In addition to this coupling to wiring by fields penetrating the building, one must also consider the coupling to external control cables and other cables penetrating the building, such as conduits from security cameras and antennas. These levels can vary considerably based on the grounding and bonding of these cables as they enter. Also, for the control cables in trenches, IEC 61000-2-10 [12] provides information on the levels of E1 HEMP currents and voltages appropriate for above-ground and buried cables.
Since control houses are typically not very large and are often constructed of reinforced concrete, it is possible to add external metallic sheeting or internal “shielded” wallboard to increase the shielding effectiveness of the building. Also, if there is some extra-sensitive equipment inside the building, a shielded rack or room can be built inside. If there is a plan to upgrade the internal electronics to newer technologies, a last option would be to remove the existing building and rebuild it as a metal building, which tends to provide higher levels of protection. Note that this does not require a “perfect” 80-100 dB building, but rather a typical bolted metal building that can be built off-site and transported to an existing concrete pad.
Separately, since the resistive grounding for lighting transients is often not sufficient, all external cables should be evaluated to ensure that they are grounded properly for high frequency transients. For shielded control cables, one should ground them before entry into the building to metallic surfaces (using U clamps, not ground wires). If the building is of concrete construction, then a metal plate can be mounted on the side of the building and connected to the grounding grid. Ideally, the bonding should take place below the surface of the earth, so the cable itself is not exposed to the air after the bonding.
This procedure has been applied with good success for several existing control buildings. Of course, it is recommended that, if unshielded cables are used for the control cables, these should be converted to shielded cables or fiber optic cables (according to the new power substation communications standard IEC 61850-3 [13]). A recent design has used fiber optic control cables according to this new IEC standard, reducing its vulnerability to HEMP and IEMI [14].
Once the reductions of internal wire currents and voltages are completed, it is still possible that the reductions won’t be sufficient with respect to the immunity of the equipment. In these cases, it may be possible to use internal wire metallic conduits, ferrites, and, in the worst case, surge arresters. The latter is not the best choice as there will be a need to test and replace surge arresters over time. Also, surge arresters designed for very fast transients are not easy to find and may be very expensive (most lightning surge arresters operate too slowly to be effective).
A final point to mention is that for the IEMI threat, distance between the attacker and the control house is very important, as the fields fall off rapidly from any EM weapon. All substations are fenced around the outside to keep the public away from hazardous electrical voltages, currents, and fields. In fact, many substations are now using solid fencing instead of chain link to reduce the potential threat related to attacks using firearms. A solid material will provide additional attenuation to an attacker at the fence position, and any effort to move further back to find an elevated position to illuminate a control house will extend the distance and reduce the field on “target.” As part of IEMI assessments, I have participated in evaluating the best locations for line-of-sight attacks on multiple control houses, and often the fields that would be directed on a control house can be reduced by factors of 2-10 based on extended ranges and opaque fencing.
Although the electronics inside the control houses are protected from natural high voltage transients, the frequency content and levels of the E1 HEMP and IEMI fields exceed the normal EMC protection methods found in these buildings today. This is mainly due to the fact that the EM shielding of the control houses is much higher for lightning fields than it is for E1 HEMP/IEMI, and the cable grounding techniques are only adequate for lightning.
This means that an assessment method is needed to evaluate the situation for existing control houses and their control cable system. In this article, we have detailed a method that has been applied to over 100 control house buildings. We have also presented several methods of improving the protection of these buildings from E1 HEMP and IEMI by examining different grounding methods, the use of shielded cables, the use of ferrites, etc., through laboratory and installation measurements.
Given that there are multiple methods available to reduce the susceptibility of the important equipment inside the control houses, it is possible to evaluate the effectiveness and the cost of these options. In addition, for those power companies who are upgrading the electronics and communications protocols in their substation control houses, it is possible to develop a specific protection approach that can be replicated over and over.
One last point I want to emphasize is that while E1 HEMP and IEMI are very unusual, and hopefully, low probability threats, the protection methods to be used are found within the EMC “toolbox.” Ultimately, it is a matter of defining the requirements for protection as opposed to developing new protection methods.
- IEC 61000-6-5 Ed. 1.0 (2015-08-21): Electromagnetic compatibility (EMC) – Part 6-5: Generic standards – Immunity for equipment used in power station and substation environment.
- IEC/TS 61000-5-10 Ed. 1.0 (2017-05-18): Electromagnetic compatibility (EMC) – Part 5-10: Installation and mitigation guidelines – Guidance on the protection of facilities against HEMP and IEMI.
- William Radasky, “Protecting Industry from HEMP and IEMI,” Feature article in In Compliance Magazine, November 2018.
- Kenneth Smith, “Plot of analytic formulas selected by the IEC to describe the three phases of the high-altitude electromagnetic pulse,” Metatech Corporation, April 1992.
- IEC 61000-2-9 Ed. 1.0 (1996-02-19): Electromagnetic compatibility (EMC) – Part 2: Environment – Section 9: Description of HEMP environment – Radiated disturbance.
- Richard Hoad, “Frequency domain comparison of IEMI environments with other transient waveforms,” Personal Communications, November 2016.
- IEC 61000-4-4, Electromagnetic compatibility (EMC) – Part 4-4: Testing and measurement techniques – Electrical fast transient/burst immunity test.
- IEC 61000-4-25 Ed. 1.2 (2019-12-11): Electromagnetic compatibility (EMC) – Part 4-25: Testing and measurement techniques – HEMP immunity test methods for equipment and systems. Basic EMC publication
- IEC 61000-4-5, Electromagnetic compatibility (EMC) – Part 4-5: Testing and measurement techniques – Surge immunity test
- Edward Savage, James Gilbert and William Radasky, “Expedient Building Shielding Measurement Method for HEMP Assessments,” IEEE Transactions on Electromagnetic Compatibility, Vol. 55, No. 3, June 2013, pp. 508-517.
- IEC 61000-2-13 Ed. 1.0 (2005-03-09): Electromagnetic compatibility (EMC) – Part 2-13: High-power electromagnetic (HPEM) environments – Radiated and conducted.
- IEC 61000-2-10 Ed. 1.0 (1998-11-24): Electromagnetic compatibility (EMC) – Part 2-10: Environment – Description of HEMP environment – Conducted disturbance.
- IEC 61850-3 Ed. 2.0 (2013-12): Communications networks and systems for power utility automation – Part 3: General requirements
- Eric Easton, Kevin Bryant, and William Radasky, “Design approach for HPEM mitigation for electrical substations,” IEEE EMC Symposium, Reno, Nevada, July 2020, pp. 439-441.